05 October 2012

South Retaining Walls and West Footers

The forms and rebar are ready.  The pump truck is here.  The South retaining walls and the West footers will be poured today.  Here are pictures of the prep work. (I thought I had pictures of the footers - need to download the camera which is taking pictures of the action at present...)  The footers are 'pretty' in their curved-ness.  Too bad they will be buried and covered in concrete.  You'll have to see in the next post.
South Retaining Wall - East side

South Retaining Wall - West side

South Retaining Wall - West side
 

27 September 2012

North Retaining Walls - Before and After Pictures

First, the process of making those walls:
Arrival of the Concrete Pumper Truck
The pumping process

  The contractor had thought he needed a bigger pump truck.  It was not available, so this 39 meter truck came and it was  just able to stretch to all needed areas.   (It saved some money.) In the photo on the left, the man in the foreground is controlling the concrete being pumped, and the boom on the pump truck.  The man above in the background is doing the final positioning of the 'nozzle' down into the wall area.  The two other men at this point are looking on.  They are waiting to get in there with their vibrator to get air bubbles out. They are working on the East retaining wall on the North end of the house.
Below, the pump operator is to the right.  This is the West retaining wall on the North end of the house.












Now for the before and after pictures.
 

20 September 2012

Forming Retaining Walls

The North Retaining Walls are taking shape. The pipe lying on the footer is an earth tube which will go thru the wall.  There is another earth tube under the footer.  These earth tubes will furnish air to the West Annex (upper and lower).
West Retaining wall on North end of house
East Retaining Wall on North end of house
 And the footers on the South end are started.  It is estimated that 6 hours more work to complete the walls and footers for the next pour (of all 4 - 2 footers and 2 walls).

15 September 2012

North Footers IN

Thursday was the first pour day.  
North Wall - East side footer

North Wall - West side footer

North Wall - West side footer
 The South Wall footers are being formed and the North Walls are being formed with a possible pour date of Tuesday - Wednesday, though the weather may be a factor in that.


North Wall - East side footer with wall stubs

Supports for Back of North Wall - West side
Form of Back of North Wall - West side

 We had a misplacement of the South Wall footer on the East side due to a misunderstanding of where the actual wall of the house is.  The wooden structure on the South side is the parapet form which is temporary;  so some extra work needs to be done to the key (the lowest part of the footer that is directly under the wall) to 'relocate' it 4 inches.
South Wall - East side footer started
 

12 September 2012

Retaining Walls for the House



 We have some more displaced dirt, and some more holes in the ground.  Materials are on site for future use. And contractors on site. The excavating crew is finished digging. Another talented Mexican crew is twisting wire and placing forms and rebar for the footers today. The weather is great and concrete is scheduled to be poured Thursday, TOMORROW at 8:30.



We have some more displaced dirt, and some more holes in the ground.  Materials are on site for future use. And contractors on site. The excavating crew Another Mexican crew is twisting wire and placing forms and rebar for the footers today. The weather is great and concrete is scheduled to be poured Thursday, TOMORROW at 8:30.

25 August 2012

Retaining Wall Delay but other work continuing

We have obtained engineered drawings of the retaining walls and accepted a proposal to build them.  The contractor will be starting right after Labor Day.  The site is ready for them.
Meanwhile, Bill and Keith and Carol have still been working,  on the garage, on the grounds, and some on the house. 

On the garage, the end wall sheathing is finished and Tyvek applied.

They removed dirt from behind the retaining walls, smoothed the joint between the retaining wall and the end wall of the garage, put a waterproofing membrane in place on that seam, inserted insulation in the form of blueboard, and back-filled again.  In the process, Bill (and the skid-steer) unearthed some snake eggs which have since hatched - hog nose snakes.
 Some insulation was inserted between the earth tubes and the garage wall.  

 


Watershield was applied to the top of the parapet to protect the joint between the wood and shotcrete. Here, you can see the watershield, the membrane and the insulation in place.


the earth tube shown from inside the structure
 The earth tubes on the house are set but need some more supporting structure before shotcrete.

Some rebar ties were found to be missing or loose and they are fixed.  And more may be found as one of the next projects is to patch holes in the burlap, and in climbing on the structure, other flaws found will get fixed.



04 July 2012

Progress Continues

Last Wednesday, the carpenters finished the work that we needed in order to get the retaining walls started.  They have left, and shall return to do some props before the shotcrete starts.  
It is very quiet on the site with no hammers, saws, pneumatic tools, drills, or Spanish-equivalent of four-letter words.  And they sing too, but not often enough for me.

But progress continues with the rebar. Bill, Keith and I (mostly Bill) are working on this big job.  It is tedious more than difficult.  Bill is concentrating on the work around the parapets.  It includes what he calls the sunrise and the rainbows.  Still to be done is a rebar 'ladder' arch reinforcing the contour change from quonset to parapet.  The North and West parapets have the black ice and water shield whereas the South is bare plywood as it is just a form and will be taken down a few days after the shotcrete.
North Parapet

West parapet

South Parapet


Keith and I are doing the quality control on the mesh and rebar.  This ensures that the 6x6 mesh is tied into the horizontal (first layer) of rebar.  We have completed all that one can reach by standing on the slab, and everything that is above the second floor.  Still to do, are the West Annex and the 18 x 40 cathedral ceiling and the South patio. The tunnel is totally done with all rebar and only needs the earth tube to be put in place.

Keith and Bill are putting on the third layer of rebar, and that is to be completed soon on the main 40 x 66 structure.   Tomorrow, the fourth layer starts.  The West Annex (except for final QC) and the Tunnel have been done (they only need three layers being smaller structures).

One of the problems the carpenters and Bill worked out has to do with the South parapet.  The steel arches are bowed such that the center is plumb, but the sides bow inward.  Some forms have been incorporated in the parapet that will 'hide' this flaw with shotcrete. 

The SE wall has a gap where blocks have been placed
The gap is covered by form to hold shotcrete
 
The SW side showing blocks in gap
SW side showing form over gap
 


At the TOP
Hopefully, the retaining walls will be started any day now.