We have had about a week without rain. The Sterrett Co has been here off and on working on the preparations for the slab - footers. They also poured the floor of our sunken area.
The plumbers, namely Glen and Mark, have been here Wednesday thru Friday, and done remarkably putting in our 13 of 14 earth tubes. One more to go. And they will come back Monday to do the last one and get the actually 'plumbing' (water drain stuff) installed. Then on Tuesday, the footers will be poured. And Wednesday is scheduled to be the BIG day where the slab will be poured. Mr Sterrett said they would be here from 4 am until 5 pm. So everything has to be ready for them.
Only problem is that there is a 50% chance of rain Tuesday night.