The I-Joist remediation is complete. The electrician has been notified.
The carpenters were here last week and put up the half wall in the kitchen and all the stud work under the stairway. They also framed the areas in the living room that will house lights and wiring.
The concrete finishers were out Saturday (almost 2 weeks ago) and finished the overhang on the South side of the house. They also smoothed (parged) the back of the garage parapet.
Bill and I painted the cold cellar floor. It is now ready for the water tank to be installed.