27 March 2012

Overhead Door Installation

Today, the garage overhead door was installed. Here are two BEFORE pictures, taken even before the retaining walls and shotcrete were done.

And here are two AFTER pictures, so you can see the wall from the exterior and from the interior.

 

24 March 2012

Many Small Accomplishments and One Completion

The INSIDE of the Garage was shot with mortar last week.
BEFORE

DURING

AFTER
Other MAJOR accomplishments, though taken singly, small things, are that the erosion control is still under control; one of the earth tubes was extended to within one connection of the retaining wall;  a lot of chipping away at shotcrete that adhered to the garage floor, scaffolding and tools created a better, safer environment; garage overhead door was ordered to be installed within a week or two, hopefully; of the many stucco procedure possibilities, we decided on one for the garage South facing wall; our excavation man, another Dan, visited and work was discussed and agreed to start next week; the burlap 6x6 panels awaiting installation have been moved to accommodate excavation; a path was created on the East side of the garage to enable ease for backfilling to occur; and we enjoyed the spring weather; and we are in the process of getting contractors lined up to work on the house.

 

09 March 2012

WE ARE ROLLIN'

The shotcrete crew came back Wednesday and cleaned the surfaces of the shotcrete and of the retaining walls. They also took off the form over the parapet.  Thursday, they applied the first coat of waterproofing.  Friday, after 0.4 inches of rain during the night, they applied the second coat of waterproofing.
From this angle, it kinda looks like the Sphinx

Dan made the suggestion that we could use the waterproofing, SikaTop Seal-107,  on the interior, masking the steel arches and then spraying on the waterproofing; that it would give a good finish. Any other finish, he thought, would need a better surface to adhere to than the burlap and 6x6 mesh - which would mean an additional step.

06 March 2012

The Garage has a PERMANENT Roof

On Thursday, the shotcrete crew got set up, and started shooting before 1 pm.  Jeremy was the main nozzleman.  Dan handled the switch on the pump and PR with the owners.  Chris and another helper were handling the hose, scaffolding and anything else so the job got done.  The owners were offered a chance to man the nozzle, but both declined.

We had some rain the day before (about 1 1/2 inches).  The job site was quite muddy.  Behind the retaining wall, you can see the water that sits on the foundation of the retaining wall, waiting to dry up or be bailed out. The area that looks like a smile above the white pipe, is the french drain up against the slab footer.  It will be further extended along the retaining wall after the waterproofing is completed.

 


Within an hour, the crew had shot around the back and were on the other side. to a height of about 4 feet.  Where the shell is connected to the slab is the thickest shotcrete - 12 inches thick. 

Here is a 3 minute video of Jeremy making it look easy.  He wears motocross shoulder pads to rest the hose  on, a hard hat and visor for protection from any aggregate that bounces back at him, and controls the heavy hose and nozzle to ensure an even 4 inches everywhere else.


When they completed that height, they came back to the East side, and added another 3 feet.  About 16 cubic yards of shotcrete was applied on Thursday.



Friday, Bill and Carol hurried to install the second earth tube so that both earth tubes could be securely in place and covered with shotcrete.  The crew arrived around 9:30 and did preliminary work.  At about 1, they started applying shotcrete around the building again and then shot the parapet (vertical wall).  Then they came back and shot the earth tubes, and then progressed more on the 'roof'.

It started to precipitate - a gentle mist that was definitely rain by 4:30 pm.  By 5 pm, they ran out of shotcrete and couldn't finish as the concrete company had sent everybody home due to the weather being so wet, and it being Friday I suppose.  The rain got worse, and the disappointed crew cleaned up and enjoyed some hot split pea soup, bread and crackers. They had an hour and a half drive back home with the thought that they had to return on Monday.  The total shotcrete was about 14 cubic yards Friday.

Monday came and so did more precipitation, this time snow and snow mixed with rain.  No obvious progress.  Bill dug a ditch to let the earth tube under the retaining wall (that white pipe mentioned earlier marked it) act as a drain and let the water go somewhere. Tuesday the crew did finish our roof so we can no longer see all that rebar. But we can remember all the labor to tie the rebar ties.


 And there's a great deal more rebar tying to do yet on the house.  I believe the shotcrete used on Tuesday was 2 cubic yards. 

Next, Wednesday, the shotcrete crew is back again  to waterproof the structure.

24 February 2012

Excitement Arises

We are growing very excited.  Dan, the shotcrete man, was here this week and we are on his schedule for our garage to be shotcrete-d Thursday and Friday, March 1-2.

We have finished the third layer of rebar.  Dirt has been re-moved some more.  And we are working on the rebar at the parapet and front wall, tying in the retaining wall as well.  We are fixing holes in the burlap so the shotcrete won't go thru (too much).  We are investigating waterproofing possibilities. Scaffolding needs to be moved. We need to make a form at the top of the parapet to shape it (provide a stopping point for the shotcrete). And lastly, the earth tubes will be installed in the roof before that momentous date. Inspection is scheduled and pictures need to be taken and sent to the company who sent us all this steel as they want to see what we have done with it,  and give us a piece of their mind. Hopefully, it will be constructive, informative and instructive.

12 February 2012

Garage PROGRESS

On Monday, John Sterrett and Jacob came, dug, rebarred, formed, and poured the footers for the garage retaining walls.

On Tuesday, we took delivery on cinder blocks and mortar mix.












On Wednesday and Thursday, the cinder blocks were shaped into two walls, one on either side of the garage 'face'. The walls are reinforced horizontally and vertically with rebar and filled with concrete from top to bottom.

Back of East Retaining Wall
Front of West Retaining Wall

















On Friday,  Brendan, Sean, Jake and  Kunya, who made the wall, parged the wall - made the surface smooth on all sides and the top.


on to the next step(s) on our way to shotcrete!

31 January 2012

Second Layer of Rebar on Garage COMPLETE

Our rebar tying expertise has improved.  
The cold weather is not a time for tying rebar.  

With the two manual handtools, one from Gensco and one from Lowes, we can handle the 6 inch ties with loops (tool from Lowes) and the spool of wire (using the Gensco tool).  We figure that we have tied about 5000 ties in doing the two layers. One more layer to go.  And, tying in the retaining wall, the parapet and the earth tubes still to do.  Then all the rebar  for the garage will be done.

View of WEST side of garage

View of EAST side of garage
In doing the second layer, we had to tie the vertical second layer to the horizontal first layer AND the 6x6 burlap mesh underneath.  In connecting the 6x6, we created a more uniform interior surface.  The next layer should be a lot easier, using the Lowes tool primarily, and not necessitating a person on the inside and outside at the same time. So two people can be tying ties at the same time.  And climbing on the building to install the upper horizontal last layer will have an easier foothold on the existing rebar.

The Interior showing the overlap of burlap 6x6 mesh panels